What's Changing on Peachtree Just North of Brookwood Hills, and When

  • November 12, 2026

Just north of Piedmont Hospital, Peachtree Road crosses the CSX railroad on a bridge built in 1914. It was designed to carry two 60-ton streetcars and one 20-ton truck, and today it is posted with weight restrictions. On GDOT's project page, the concrete has visible water damage, with cracking, spalling and exposed rebar on the deck and pier walls, and some sections of rebar have been lost entirely.

Most people in Brookwood Hills drive over that bridge whenever they head up Peachtree toward Buckhead, and few have reason to think about it. That changes over the next two years. Three projects now overlap on the same few hundred feet of road: demolition on Bennett Street, a new Beltline trail segment, and the full replacement of the bridge. They are scheduled to happen in an order that helps people who live nearby. The trail reaches Peachtree Road first, and the bridge work that affects traffic doesn't start until 2028.

Where the work actually is

GDOT's concept layout runs the bridge project about 600 feet, from the Bennett Street area to Peachtree Valley Road NE. Urbanize Atlanta places it just north of Piedmont Hospital, next to the Bennett Street properties the Beltline now owns. That puts it on the next stretch of Peachtree past the hospital Brookwood Hills faces.

The replacement bridge will be about 130 feet long, so its supports sit outside the railroad right-of-way, with room for the existing track and one future track. It will carry six 11-foot travel lanes, with a 9-foot sidewalk on each side. Under it, a section of the Beltline's Northwest Trail is planned to cross beneath Peachtree Road.

The order of operations

Each project has its own agency and its own schedule. Here they are together on one calendar, as of the latest published dates:

When What happens Who
August 5, 2026 Demolition of six vacant Bennett Street buildings announced Atlanta Beltline Inc.
September 21, 2026 Hasbun Construction's notice to proceed signed for Northwest Trail Segment 2A Atlanta Beltline Inc.
Late October 2026 Segment 2A groundbreaking held Atlanta Beltline Inc.
By end of 2026 Bennett Street demolition expected to finish Atlanta Beltline Inc.
December 18, 2026, tentative Bridge contractor selection scheduled to be announced GDOT
Early 2027 Segment 2C construction expected to start Atlanta Beltline Inc.
Early 2028 Segment 2A scheduled to finish Atlanta Beltline Inc.
2028 Peachtree Road bridge replacement scheduled to begin GDOT

Clearing and trail building fill the next year and a half, and the bridge replacement follows in 2028.

Bennett Street this month

The demolition is the part you can see from the road right now. The Beltline bought six parcels where Peachtree Road meets Bennett Street in 2025, after buying the former Elleven45 Lounge and the property next to it in 2024. Urbanize Atlanta reported that the agency paid $29 million in total for 3.2 acres, its first purchases along the Peachtree Road corridor.

Crews have been taking down the six vacant buildings, which total 75,000 square feet, and the former Elleven45 building has already been razed, according to Urbanize Atlanta's October 27 report. The Beltline expects demolition to wrap up by the end of 2026, and businesses at the western end of Bennett Street are staying open while it goes on.

The cleared land has more than one job. It opens a trail corridor where none exists today, and it gives GDOT room it needs for the bridge work and staging. Over the longer term, Beltline officials have said the site will hold commercial space and non-market-rate housing.

The trail gets to Peachtree before the bridge work starts

Segment 2 of the Northwest Trail runs about 0.7 miles east from the southeast corner of Bobby Jones Golf Course along Colonial Hills Circle. The Beltline is building it in three sections, and the order is what matters for Brookwood Hills.

  1. Section 2A, under construction now. This 0.3-mile piece branches off the finished trails around Bobby Jones Golf Course and heads east toward Peachtree Road. It connects Collier Hills North and Colonial Homes. The scope includes a 14-foot multi-use trail, a pedestrian bridge, an elevated trail structure and Trees Atlanta landscaping. It is scheduled to finish in early 2028.
  2. Section 2C, expected to start in early 2027. This 0.1-mile section runs from Peachtree Road to Peachtree Park Apartments.
  3. Section 2B, tied to the bridge. This is the permanent crossing under Peachtree Road. The Beltline is coordinating it with GDOT and the Buckhead Coalition, and it will be built as part of the bridge replacement.

The 2A contract also covers a temporary trail connection to Peachtree Road, with new pedestrian-friendly traffic signals for safer crossings while the remaining sections are finished. The Beltline plans an interim at-grade crossing of Peachtree during the bridge replacement, then a permanent trail under the new bridge. So the trail reaches Peachtree through a signalized street crossing first. The crossing under the bridge comes later, once the new bridge is built.

For Brookwood Hills, that puts a trail entrance within reach on Peachtree, connected west to Bobby Jones and the Collier Hills trail network, years before the full under-bridge route exists. It also puts a Beltline trail point near Piedmont Hospital and the Shepherd Center, which together make up the largest jobs hub along the 22-mile loop.

Segment 1 is a separate piece just to the east. It runs 0.8 miles from the west side of Peachtree Park Apartments south along Peachtree Creek. The Beltline's September update says its bridge over Peachtree Creek is being removed and rebuilt to fix an engineering issue, with a current target of mid-2028.

What GDOT's early plan says about closing Peachtree

This part matters most for anyone who drives Peachtree daily, and the plan will be firmed up once the contractor is chosen. GDOT is using a Construction Manager/General Contractor approach, and its project page says details may change after the award. The tentative procurement schedule calls for proposals on November 19, 2026 and a selection announcement on December 18, 2026.

The current picture comes from GDOT's April 2025 response to public comments, written before procurement. GDOT's preferred approach uses accelerated bridge construction, with an estimated 18 months of work. Under that plan, temporary Bailey bridges go up on the east and west sides at different times and keep at least two lanes moving in each direction for most of construction. GDOT cited the high traffic volumes and the need to protect emergency access to the nearby hospitals. The conventional alternative was estimated at 36 months with one lane each way, and GDOT did not prefer it.

Under the accelerated plan, full closures happen only while the temporary bridges go in and come out. GDOT estimated two closures of 4 to 5 weeks each. During those closures:

  • The official signed detour is about 10.1 miles, because GDOT's official detours have to use state routes.
  • A shorter local-only route of 2.8 miles is planned so residents and businesses can reach their properties. It is not a signed official detour.
  • Northside Drive is not proposed as part of the detour.
  • GDOT said it would post clear signage, including warnings ahead of detours and notices to EMS, hospital and police services.

The public comment period drew 39 formal respondents. Fourteen supported the project, four opposed it and 21 gave conditional support. Cut-through traffic and neighborhood access came up repeatedly. The Peachtree Battle Alliance told its neighbors it was tracking the project and would push for less disruption and congestion from the detours.

GDOT's project page also explains why the work can't wait. Without a replacement, the bridge would eventually deteriorate to the point of closing to vehicles, which would cut the Peachtree Road connection through this part of Buckhead. Under the plan on file, the 1914 bridge comes down, the road stays open for most of the 18 months, and the full closures add up to roughly two months of one year.

Keeping up with it

GDOT's project page expects the contractor announcement in late Q4 2026, and the tentative procurement schedule sets it for December 18. The final staging plan should follow from that choice. GDOT sends project updates through a subscription list on the project hub, and the hub links the concept layout and detour map. The Beltline posts trail progress on its Northwest Trail Segment 2 page and in its monthly construction updates. For traffic questions during construction, GDOT directs questions to its District 7 Engineer at 770-216-3890.

If you're planning a move, a renovation or a sale around the Peachtree work and want to talk timing with someone who watches this corridor closely, Ashley Altenbach is glad to walk through it with you. Contact Ashley to discuss your home or find your next in-town property.